ESEN
Aerial view of the dual carriageway and stabilisation works on the Rumichaca–Pasto corridor
← All projects

ROADS · NARIÑO

Rumichaca–Pasto

Dual-carriageway design between Rumichaca and El Pedregal.

Client
Consorcio SH (Sacyr–Herdoiza)
Period
2016–2017
Scope
44 km · Functional units 1, 2 and 3

CASE STUDY

Engineering applied to an infrastructure challenge.

Phase III design for 44 km across functional units 1, 2 and 3 of the Rumichaca–Pasto road corridor.

Technical scope

  • Geometric design and geotechnics
  • Drainage and pavements
  • Structures and bridges
  • Road signage and complementary works

Origin of the experience

Supported experience.

JORGE FANDIÑO S.A.S.Certified experience · Corporate track record

Does your project face similar challenges?

Discuss your project